Current Projects

[ Current Projects | Completed Projects | Future Projects ]

Details of Current Capital Projects

Each capital project requires approval from the Ministry of Education and Child Care. A status update is provided below. This page is updated regularly. Please note, as projects proceed and circumstances become better clarified, the dates below are subject to change.

040-kbw-addn-202307.818287196069.jpg


Snokomish Elementary New School (Site 115)

  • Address: 
  • Project Type: New School, 27 classrooms
  • Approval: Ministry of Education and Child Care approval March 30, 2021
  • Current Phase: Construction 96%
  • Construction Contract: D.G.S. Construction Company Ltd.
  • Target Occupancy: January 2026

Walnut Road Elementary Prefab Addition (Site 152)
+ Additional Four Prefabricated Classrooms (Site 152)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 12 classrooms (finished) + 4 classrooms = 16 classrooms
  • Approval: Ministry of Education and Child Care approval September 27, 2023
  • Current Phase: Construction 98% (four additional classrooms)
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: April 2025 (12 classrooms); Fall 2025 (additional 4 classrooms)

Kwantlen Park Secondary Addition (Site 048)

  • Address: 
  • Project Type: Addition, 20 classrooms
  • Approval: Ministry of Education and Child Care approval January 10, 2023
  • Current Phase: Construction 20%
  • Construction Contract: Olivit Construction Ltd.
  • Target Occupancy: Summer 2028

Guildford Park Secondary Addition (Site 047)

  • Address: 
  • Project Type: Addition, 14 classrooms
  • Approval: Ministry of Education and Child Care approval May 26, 2023
  • Current Phase: Construction 4%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: Spring 2028

Tamanawis Secondary Addition (Site 150)

  • Address: 
  • Project Type: Addition, 23 classrooms
  • Approval: Ministry of Education and Child Care approval May 9, 2023
  • Current Phase: Construction 2%
  • Construction Contract: D.G.S. Construction Company Ltd.
  • Target Occupancy: Fall 2027

Fleetwood Park Secondary Addition (Site 167)

  • Address: 
  • Project Type: Addition, 32 classrooms
  • Approval: Ministry of Education and Child Care approval June 27, 2024
  • Current Phase: Design
  • Tender: Fall 2026
  • Target Occupancy: January 2029

Forsyth Road Elementary Addition (Site 183) 

  • Address: 
  • Project Type: Addition, 14 classrooms
  • Approval: Ministry of Education and Child Care approval June 10, 2024
  • Current Phase: Design
  • Tender: Spring 2026
  • Target Occupancy: Fall 2028

Old Yale Road Elementary Prefab Addition (Site 064)

  • Address: 
  • Project Type: Pre-fabricated Modular Addition, 10 classrooms + 7 More (17 total)
  • Approval: Ministry of Education and Child Care approval May 16, 2024 for 10 classrooms; July 5, 2024 for additional 7 classrooms
  • Current Phase: Construction 5%
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: Spring 2027

Martha Currie Elementary Prefab Addition (Site 061)

  • Address: 
  • Project: Pre-fabricated Modular Addition, 6 classrooms
  • Approval: Ministry of Education and Child Care approval May 16, 2024
  • Current Phase: Construction 1%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: June 2025

Latimer Road Elementary Prefab Addition (Site 035)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 6 classrooms
  • Approval: Ministry of Education and Child Care approval July 5, 2024
  • Current Phase: Construction 7%
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: Fall 2026

William Watson Elementary Prefab Addition (Site 057)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 12 classrooms
  • Approval: Ministry of Education and Child Care approval July 5, 2024
  • Current Phase: Construction 5%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: Spring 2027

George Greenaway Elementary Prefab Addition (Site 090)

  • Address: 
  • Project Type: Addition, 14 classrooms
  • Approval: Ministry of Education and Child Care approval September 9, 2024
  • Current Phase: Construction 15%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: Fall 2026 

Clayton Heights Secondary Addition (Site 175)

  • Address: 
  • Project Type: Addition, 20 classrooms
  • Approval: Ministry of Education and Child Care approval July 4, 2025
  • Current Phase: Design
  • Tender: tbd
  • Target Occupancy: tbd

Redwood Park New Elementary School (Site 214)

  • Address: 17320 and 17390 20 Avenue area
  • Project Type: New School, 37 classrooms
  • Approval: Ministry of Education and Child Care support to proceed to PDR
  • Current Phase: Planning
  • Tender: Pending Ministry of Education and Child Care funding approval
  • Target Occupancy: Pending Ministry of Education and Child Care funding approval

Grandview Heights Secondary Addition (Site 177)

  • Address: 
  • Project Type: Addition, 20 classrooms
  • Approval: Ministry of Education and Child Care support to proceed to PDR
  • Current Phase: Planning
  • Tender: Pending Ministry of Education and Child Care funding approval
  • Target Occupancy: Pending Ministry of Education and Child Care funding approval